The order a bathroom remodel has to happen in, and why tile goes last

Every bathroom remodel has the same skeleton. The finishes change, the layout changes, the budget changes, but the sequence doesn’t, because each step covers up the one before it. Get the order wrong and you either tear out new work or live with a problem you can’t see.

Here’s the order we build in on every bathroom remodel in San Diego, and the reason behind each position. Our bathroom page shows it as six steps; this is the same sequence with the inspection, the tile and the fixtures broken out on their own, because those are the three places the order gets argued about.

Step 0: selections, before anything comes out

This is the step most people skip, and it’s the one that decides whether the job finishes on schedule. Tile, vanity, countertop, faucet, shower valve, toilet, lighting and the exhaust fan are all chosen and delivered before demo starts.

The reason is lead time. A shower valve is a few days. A vanity can be two weeks. Some tile is six. If the job starts before the materials are in hand, the schedule is now set by the slowest delivery instead of by the work. We’ve seen bathrooms sit open for a month waiting on a faucet. So we don’t open the wall until the garage has everything in it.

There’s a second reason. The shower valve has to be roughed in to match the trim you picked. The niche gets framed to the tile module. The vanity drain location depends on the vanity. Those decisions are locked at step 3, so they have to be made at step 0.

Step 1: permit

In every city in San Diego County, moving a drain, adding or extending a circuit, changing the shower footprint or touching structure needs a permit. A repaint or a like-for-like faucet swap usually doesn’t. Most real remodels do.

The permit comes first because it brings the inspector in at two points: after rough plumbing and electrical, and at the end. Those two visits are the homeowner’s independent check that the work behind the tile was done right. Permits handled is written into our contract, and we meet the inspector so you don’t have to.

Step 2: demo, down to the studs

Tile, backer board, the old pan, the vanity and the flooring come out. Demo on a typical bathroom is one to two days with dust barriers on the doorway and a protected path to the front door.

Demo is also discovery. In San Diego homes from the 1960s through the 1980s we regularly find original galvanized supply lines, cast-iron drains at the end of their life, framing that moved and a floor that’s out of level. All of it is cheaper to fix now, with the walls open, than at any later point. If something changes the scope, you get a written change order before anyone touches it.

Step 3: rough plumbing and electrical

New supply lines and drains go in. The shower valve is set to the depth the trim needs. If the layout moved, this is where the slab gets cut and the new drain is placed. On the electrical side: the fan, new lighting, a GFCI circuit for the vanity, and any heated floor or bidet circuit.

Everything in this step is about to be buried behind drywall, backer board and tile for the next 20 years. That’s why it’s inspected next.

Step 4: rough inspection

The inspector checks the plumbing and the electrical before anything gets covered. Pressure on the supply lines, drain slope and venting, box fill and wire gauge, the fan duct run. Pass, and the walls can close. Fail, and we fix it the same day and call for a reinspection.

Step 5: waterproofing, then the 24-hour flood test

Backer board goes up, then the waterproofing: pan, curb, membrane up the walls, every corner, seam and the niche sealed. Then we plug the drain, fill the pan to above the curb line, mark the water level with tape and leave it for 24 hours.

If the tape line hasn’t moved, the pan holds and tile can go on. If it has, we find the leak while it still costs an afternoon to fix. This is the step you’ll never see in a finished photo, and it’s the one that fails first when it’s skipped. We wrote a separate post on it: how we waterproof a shower before a single tile goes on.

Step 6: tile

Now, and only now, tile. Floor first or walls first depends on the tile and the layout, but either way it goes onto a tested, dry assembly. Large-format and natural stone take longer to set than ceramic, and a herringbone floor takes longer than a straight lay.

Tile goes late because it’s the one layer you can’t open without destroying it. Every inspection and every test happens before it, so that nothing behind it ever needs to be reached again.

Step 7: fixtures, then glass

Grout cures, then the vanity, countertop, faucet, toilet, mirror, lights and trim go in. Last of all, the shower glass.

Glass is measured after tile, not before, because tile thickness, a slightly out-of-plumb wall or a curb that sits a quarter inch high all change the opening. The glass is fabricated to that measurement, which is usually a week or two, so it’s the final piece installed. Anyone who promises glass the same week the tile goes up is either measuring early and hoping, or installing a stock door with filler.

Step 8: final inspection, walkthrough, punch list

The inspector signs off on the finished work. Then we walk the room with you, run every fixture, and write down anything that isn’t right. The punch list gets fixed before we call the job done, and that’s when the final payment is due.

Why the order matters more than the speed

A bathroom built in this order takes about the same number of days as one built out of order, when the out-of-order one goes well. The difference is what happens when it doesn’t. A pan that wasn’t tested shows up as a stain on the ceiling below in year two. Glass measured early shows up as a gap you look at every morning. A permit skipped shows up at resale.

We’d rather spend a day on a flood test than a week on a tear-out. That’s the whole philosophy.

Common questions

Can you tile over the old tile to save time?
Not in a shower. The old assembly’s waterproofing is unknown, and adding weight and thickness to it hides problems instead of fixing them. On a dry floor it’s sometimes possible, but it raises the floor and the transitions, so we rarely recommend it.

What if the inspector finds something at the rough stage?
We fix it and call for a reinspection. That’s the point of the inspection: catching it while the wall is open costs hours, not a tear-out.

Does the order change for a small bathroom or a powder room?
No. The steps are the same; several just get shorter. A powder room with no shower skips the pan and flood test but still gets the permit if plumbing or electrical changes.

Who orders the materials?
We do, after you’ve made the selections with us. The order goes in with the design, so it lands before demo. If you’d rather supply a specific item yourself, we’ll tell you the date it needs to be on site.

Planning a bathroom?

Call (858) 392-6767. The first call is about 20 minutes: what’s wrong with the bathroom today, who uses it and what has to change. Then a site measure and a design conversation. The price comes after design, in a fixed-price contract, with the permit and the flood test written into it. Or start with our San Diego bathroom remodeling page.